Cornwall Steel Buildings

Hay barns and straw storage

Height to stack into, air through the sides, and the frame doing nearly all the work. Tell us roughly what you need and you get engineered drawings and a price — and this is the one building where the honest answer about the floor might be that you do not need one.

Common span
9–18 m

Work it out in bales across, not in round metres.

Typical slab
150 mm

The lightest on the list. Some barns get away without one.

Sub-base
150 mm

Compacted Type 1, spread around 190 mm loose.

Topsoil to shift
81 m³

More than twice the concrete volume, and the figure most people guess.

What you are actually buying

The simplest building on the place and the one where the frame does almost all the work. Open or part-clad sides, height to stack into, and enough air moving through it that the crop keeps. The load is heavy but it is dead and evenly spread, which is why the floor question here is different from every other building on this site.

Span is bale geometry

Work it out in bales rather than metres — how many across, stacked how high, loaded from which end. A span that wastes half a bale width across the building wastes it in every row, for the life of the barn.

Length is the cheap dimension

Bays at 6 metre centres, and each one costs less per square metre than the last. If storage is the whole purpose, extra length is the best value on the quote.

Height is stacking and air

Tall enough to stack to with the handler you actually own, and open enough at the eaves that air moves through the stack rather than sitting in it.

What you get asked to decide

  • Open sides, part-clad, or space boarding to keep driving rain off the outside rows
  • Which end you load from, and whether that end stays fully open
  • Fibre cement roof sheets, which breathe better than steel over a damp crop
  • Whether it gets a slab at all, or a compacted stone floor with a concrete apron
  • Supplied for your own team to erect, or supplied and erected

How it goes from here

Five steps, in this order. The fourth is the one nobody prices for you up front, which is why there is a calculator further down this page.

  1. Step 1

    Tell us roughly what you need

    Span, length and what it is for. Approximate is fine — nobody expects you to have decided, and it means the first reply can be useful rather than a list of questions.

  2. Step 2

    Drawings and a price for the frame

    A steel building supplier prepares engineered drawings and quotes the building. That includes the pad foundation sizes, which no calculator can work out for you.

  3. Step 3

    Settle the planning position

    Prior approval on a qualifying agricultural holding, or a full application. Worth establishing before steel is ordered rather than after.

  4. Step 4

    Get the base in

    Site strip, level, stone and slab, ready and cured before the erectors arrive. This is the part you can price on this page today.

  5. Step 5

    Delivery and erection

    Delivered for your own team to put up, or supplied and erected. Both are normal; the difference is worth asking about at quote stage, not later.

Get a price for my hay barn

Rough dimensions are enough to start. You get a reply the same day.

Bales are an easy load

A stack of bales is heavy, but it is heavy in the way a slab likes: spread out, sitting still, in the same place all winter. Nothing turns on it, nothing jacks up on it, nothing drops a loaded bucket on it. That is why 150mm with mesh does a hay barn when a machinery store wants 200mm.

Plenty of hay barns run on compacted stone with no slab at all, and there is nothing wrong with that if the building will only ever hold fodder. What the slab buys is a clean, dry, sweepable floor, the bottom row of bales kept off the ground, and the option of using the building for something else in ten years.

The sub-base is not the variable

This is the thing worth knowing before you decide. Whether or not you pour a slab, you still strip the topsoil, still level the platform, and still lay and compact the stone. The groundworks happen either way.

81 m³

Topsoil to strip off the working platform for a 12 × 18 m barn at 250 mm depth — more than twice the volume of the concrete. Whether you lay a slab or not, that muck still has to go somewhere.

So when you price the slab against no slab, you are pricing 35 cubic metres of concrete and the mesh, not the whole job. The earthworks and the stone are already spent. That usually makes the slab a smaller decision than people expect.

Spec it for what it will end up being

Farm buildings change use. A hay barn becomes somewhere to park a trailer, then somewhere to keep the sprayer out of the frost, then somewhere the telehandler lives. Nobody plans it and it happens on most farms.

The difference between a 150mm hay barn floor and a 200mm machinery floor on the same building is about ten cubic metres of concrete. Relaying a floor that turned out to be too light, with a building already up over the top of it, costs an order of magnitude more than that. If there is any real chance the building ends up holding machinery, spec it now.

Dry fodder and fire

More hay is spoiled by damp coming up from the ground or rain blowing in through an open side than by anything to do with slab thickness. Ground levels around the building, where the water goes when it runs off the roof, and which way the open side faces are worth more attention than the concrete specification.

Fire is the other one. Stored hay and straw carry a genuine fire risk, and it is a reason to think about where the building sits relative to everything else on the yard rather than putting it in the most convenient gap. Worth a conversation with your insurer and with whoever is designing the layout, at the point where moving it still costs nothing.

Planning

On a working holding a hay barn is usually agricultural development rather than a full planning application. Part 6 of the General Permitted Development Order gives rights on agricultural units of five hectares or more under Class A, and narrower rights on units between 0.4 and five hectares under Class B. The building has to be reasonably necessary for agriculture on that unit.

Rather than a planning application you apply to the council for a determination on whether prior approval is needed for the siting, design and external appearance, and they have 28 days to respond. There is a floor area limit that has moved twice — it was 465 square metres until 2018, rose to 1,000, and was amended again in May 2024, so check the current position rather than an older guide.

Rights are restricted on protected land, which covers a substantial part of Cornwall, and scheduled monuments were added to the exclusions in 2024.

A summary, not planning advice. The legislation is Part 6 of Schedule 2 to the Town and Country Planning (General Permitted Development) (England) Order 2015, as amended. Talk to Cornwall Council about your own site.

Work out the base for your hay barn

Set to a hay barn specification. A 12 by 18 at 150mm comes out around 35 cubic metres of concrete. To compare it against a machinery floor, change the slab thickness to 200mm and watch the figure.

Building

Storage only — the lightest slab on the list.

m
m

Slab

Set by the building type above. Change it if you know different.

mm

Each side. Leave at 0 if it finishes flush.

mm

Site

mm

High corner to low corner.

Balanced keeps the dug material on the plot and moves the least.

mm

Dig a trial hole and measure it. This shifts more muck than the slope does.

Concrete to order for the slab
39.0waste allowed, rounded to the half metre
Hay barn · slab 246.4 m² at 150 mm · working platform 352.6
Ready-mix plant
Slab concrete
Net 37.0 m³ before waste
39.0
Quarry
Type 1 sub-base
Spread 188 mm loose to finish at 150 mm compacted
77.6t
Builders merchant
Mesh sheets
2.4 × 4.8 m sheets, 300 mm laps allowed
28sheets
Damp proof membrane
Laps and upstand included
276
Edge detail
Perimeter, for edge insulation or expansion joint
64.8m
Earthworks
Topsoil to strip
110.2 m³ once dug and loose
88.2
Cut
17.6
Fill
17.6

What this does not work out: the pad foundations

The concrete pads the stanchions sit on are sized by a structural engineer, not by a formula. They change with the span, the eaves height, the wind loading on your particular site and what the ground will bear. Anyone quoting you a pad size without a design has guessed it.

Want this priced properly?

Send us the job and we'll get you engineered drawings and a quote for the frame — with the pad sizes this tool can't work out. The figures above go with your enquiry, so you don't have to type them again.

Every enquiry gets a reply the same day, and your figures are sent with it. We are not a steel building manufacturer — we pass your details to a steel building supplier so they can price the job and contact you. How we handle your details.

Common questions

What span should a hay barn be?
Work it out in bales rather than in metres. Decide the bale size you actually make, how many you want across the building and how many rows deep you can reach in with the handler, and the span follows from that. A span that wastes half a bale width across the building wastes it in every single row, for the life of the barn — which is the difference between a barn that holds the crop and one that nearly does.
Should a hay barn have open sides?
Air moving through the stack is what keeps the crop, so most hay barns are open on at least one side or clad only part way up. The trade-off is driving rain, which will spoil the outside rows on an exposed Cornish site. Space boarding or a part-height sheet is the usual compromise: it breaks the rain without stopping the air. Which side you leave open should be decided from the prevailing wind and from where you load, not from which side faces the yard.
Does a hay barn need a concrete floor at all?
Not always. Bales are a distributed load and they are not driven over the way a machinery store floor is, so plenty of hay barns run on compacted stone rather than a slab. What a slab buys you is a clean, dry, sweepable floor that keeps the bottom row of bales off the ground and lets you use the building for something else later. If you are undecided, price both — the sub-base is needed either way, so the slab is the only variable.
How thick should a hay barn slab be?
Where a slab is laid, 150mm with mesh is the usual specification and it is the lightest of the farm building types. Stored bales sit still and spread their weight, so the floor is not doing the work a machinery store floor does. If there is any chance the building will end up storing machinery instead — and there usually is — spec it as a machinery store now rather than relaying it later.
What matters more than the floor in a hay barn?
Keeping the fodder dry and thinking about fire. Damp from below or wind-driven rain through an open side will spoil more hay than a thin slab ever will, so falls, ground levels around the building and which way the open side faces are worth more attention than concrete thickness. Fire is the other consideration — stored hay and straw carry a real fire risk, which is a reason to think carefully about how close the building sits to other buildings on the yard.
Do I need planning permission for a hay barn?
On a qualifying agricultural holding it is usually permitted development rather than a full application. Part 6 of the GPDO gives rights on units of five hectares or more under Class A and narrower rights on units of 0.4 to under five hectares under Class B, provided the building is reasonably necessary for agriculture on that unit. You apply to the council for a prior approval determination on siting, design and external appearance, which they have 28 days to decide. Rights are restricted on protected land, which covers a substantial part of Cornwall.

Get a price for your hay barn

Rough span and length is enough to start with, and say how high you want to stack — it decides the eaves. You get engineered drawings and a price, including the pad foundation sizes.